Risk Matrixes as Environmental Management Tools

Written By

Alice Elizabeth González, Martín Paz Urban, Martín Goyeneche and Lady Carolina Ramírez

Submitted: 07 May 2024 Reviewed: 15 May 2024 Published: 18 June 2024

DOI: 10.5772/intechopen.1005677

Recent Topics in Highway Engineering - Up-to-date Overview of Practical Knowledge IntechOpen
Recent Topics in Highway Engineering - Up-to-date Overview of Pra... Edited by Salvatore Antonio Biancardo

From the Edited Volume

Recent Topics in Highway Engineering - Up-to-date Overview of Practical Knowledge [Working Title]

Dr. Salvatore Antonio Biancardo

Chapter metrics overview

8 Chapter Downloads

View Full Metrics

Abstract

Within the framework of a broader project, the vulnerability to climate change of roadworks of art (bridges and culverts) was analyzed. A hydrological study was done; a set of preselected bridges and culverts was characterized. A methodology was proposed to work with risk matrices in order to determine an investment prioritization criterion from this point of view. This methodology was applied to the preselected set of bridges and culverts intended to have higher vulnerability to climate change (because of their years in service, their design, current scour depth, and so on). The proposed methodology was implemented in detail in two specific cases and turned out to be robust and easy to apply.

Keywords

  • risk matrices
  • climate change
  • vulnerability
  • environmental management
  • bridges and culverts

1. Introduction

1.1 Risk and risk assessment

Risk can be defined as the probable damage that a disaster can cause according to certain conditions of threat and vulnerability (Ferradas in [1]). Risk implies the existence of future or hypothetical damages, the occurrence of which depends on certain conditions that can be assumed to be human or environmental causes (Hurtado et al. in [1]). Some disasters are caused by environmental phenomena that cannot be neutralized, although in some cases they can be partially prevented.

Thus, risk is defined as a combination of the probability of an event occurring and its consequences, including its severity [2]. The identification and assessment of risks is carried out through the analysis of threats (natural or anthropic phenomena that may arise) and the vulnerability of potential recipients. Risks are identified and assessed through methodologies that consider the probability of occurrence of a risk event and its consequences, in order to determine the level of current risk [1].

The IPCC’s approach to vulnerability and risk is now broader than the “classical” approach that used to be focused on extreme events, probability, and uncertainty. Through a comprehensive vision, Cardona et al. [3] propose that:

“Understanding disaster risk management as a social process allows us to change the focus of disaster response toward an understanding of disaster risk (…). This requires to know how human interactions with the natural environment lead to the creation of new hazards and how people, property, infrastructure, assets, and the environment are exposed to potentially harmful events. Furthermore, it requires an understanding of the vulnerability of people and their livelihoods, including the allocation and distribution of social and economic resources that can work for or against the achievement of resistance, resilience, and security.”

When referring to extreme events, vulnerability may be less critical than for the case of events with a higher probability of occurrence and lower intensity. However, for the latter, vulnerability has a strong relationship with small and recurring disasters. To promote more resilient societies with greater adaptive capacity, it is necessary to understand what risk is about and learn to manage it. Anticipating the occurrence of an adverse event, being able to prevent it or capitalizing on the consequences of an event to reduce the impact of future events, may contribute to reducing risk and, consequently, to better allocate resources. Reducing the exposure and vulnerability of a certain community to a type of event might increase the risk for another community in the area; this is why it is necessary to assume the need of a plan with a systemic approach [3]. Risk management aims to reduce the probability of occurrence of the adverse impacts of an event. Risk can be represented in several ways, but here it will be seen as a function of the danger or threat and the vulnerability or susceptibility of the recipient to being overwhelmed by that danger. Therefore, correctly determining the factors involved will help create a clear and representative risk matrix.

The existence of a risk will imply the presence of a disruptive agent or hazard, which is likely to cause harm. These adverse effects will be of different nature and intensity depending on the level of vulnerability of the infrastructure that is affected [4].

According to [5], risk analysis should always be a participatory process developed with the community, with or without information generation or explicit engineering participation. When using engineering analysis, two components must be quantified: the probability of the risk and the severity of its consequences. The probability of the risk is the probability of failure of the system or one of its elements. The consequences and their severity can be obtained by applying typical engineering tools, which classify the risk according to the expected consequences and whether or not they are acceptable for the cultural thresholds of the place [6].

Vulnerability and risk assessments are key strategic activities that inform both disaster risk management and climate change adaptation. They require the use of reliable methodologies that allow adequate estimation and quantification of the potential losses and consequences of a risk event for human systems, in a given exposure time. At the local level, there is usually a lack of information to carry out a detailed analysis. However, it is desirable that these evaluations can be carried out locally to achieve the best possible result for a given community [7]. Therefore, it is common to have to resort to criteria to simplify or aggregate the available information since either basic quantitative information is missing or the information available does not have the level of detail that would be useful.

The most common way to represent the probabilistic nature of hydrometeorological phenomena is in terms of a return period Tr, which is the period of time that, on average, elapses between the occurrence of phenomena of a certain intensity [8]. The aim is to model using different return periods and obtain a range of responses to different scenarios. Therefore, the dangers have to be identified, enumerated, and determined, maintaining short- and long-term perspectives, taking into account the duration and intensity of the events, and performing an analysis of the suitability of the territory, that is, prepare a diagnosis of the location area and the current condition of each bridge. The level of detail achieved by this analysis will depend mostly on the availability of the data. On the other hand, the considered characteristics of the hydrometeorological events of interest must be carefully chosen, in order to obtain a representative set of factors to evaluate.

In European countries, there are systematic studies on the risks involved in major floods, focusing on their multisectoral consequences [9, 10]. Risk indicators include the occurrence of heavy rainfall, such as a history of flooding that can generate adverse impacts on the socioeconomic system and ecosystem services. These include flash floods, the frequency of which is expected to increase, especially in summer. Directive 2007/60/EC, the current version of Directive 2000/60/EC on operational aspects of the water policy of the European Union, is currently in force [9]. Among other provisions, the current directive suggests the construction of flood risk maps and the development of flood risk management plans, with a focus on prevention, protection, and training of people. The abovementioned directive requests flood extent maps for a scenario of low probability of occurrence (the return period is not established, but some countries have used 300 years and others, such as Sweden, have used the flood of Tr = 10,000 years) and another with medium probability (Tr ≥ 100 years). The expected flood limits should be presented on a chart, together with roads, buildings, water bodies, and so on. For flood management, it may be also useful to map the water depth, the flow velocity, or its danger (as a combination of the return period and the severity of the event), among other information [10].

Article 4 of the directive indicates the following minimum contents for the preliminary flood risk assessment; regarding the content of flood danger maps and flood risk maps, their content is also established in the directive. For threat maps, three scenarios with different probabilities of occurrence must be considered [9]:

  1. “low probability of flooding or extreme event scenario;

  2. average probability of flooding (return period ≥ 100 years);

  3. high probability of flooding, when applicable.”

For each of them, the extent of the flooding, the water depth, and, where appropriate, the corresponding flow velocity must be indicated. For flood risk maps, the approximate number of inhabitants that may be affected, the economic activities within potentially affected areas, and the identification of facilities that may cause pollution problems during a flood must also be presented [9].

The flood emergency management system (FEMS) is also operational in the European Union [11]. The European Commission, through its EU STAR – FLOOD1 project, proposes a new way to assess and monitor the effectiveness of FEMS, applying seven indicators that must be evaluated at the national level: planning (if there is an operational plan in case of emergency due to flooding); institutional learning (e.g., post-event reviews and consultations, opportunities for knowledge exchange between responding agencies); emergency situation drills; joint work; community training; provision of resources; and recovery-based activities. A scale of one to five is used for each criterion. As both the frequency and severity of floods are expected to increase due to climate change, societies must prepare to cope. Therefore, the evaluation was implemented in five countries (France, Netherlands, Poland, Sweden, and the United Kingdom, more specifically, England) [11]. As a result, important differences were evident between different countries in terms of the risk of suffering floods. For example, the consequences on infrastructure, for example, bridges, are included in the section related to risks for economic activity. The countries that have reported a greater number of vulnerable points for events with a medium probability of occurrence are Italy, Spain, Portugal, and the United Kingdom. From this primary evaluation, several opportunities and constraints are identified to improve the effectiveness of FEMS in Europe. Therefore, the assessment framework is an important factor in impulse further research in this area [12].

An interesting precedent is presented in Ref. [13]. The work presents the development of a method that uses GIS tools to evaluate the danger, vulnerability, and exposure to flood risk in an area of Salamanca. A nonstructural measure is proposed for the prevention and mitigation of the risk of extraordinary floods. The methodology used to analyze the flood risk was based on the exploration of the physical environment, and it was used in a combined and complementary way for the hydrological-hydraulic model using GIS (ArcGis 10.1). Hazards, vulnerability, and exposure were mapped, with the final objective of evaluating risk through the multiplication of the values of these three elements [13].

1.2 The Fine’s matrix

Currently, many of the quantitative tools for risk analysis derive from William Fine’s matrix (1971, as mentioned in Ref. [14]), which has derived in what is currently known as the “risk matrix”. Risk matrices are usually applied both in occupational safety and environmental issues, business risks, and other applications, due to the ease with which it allows interventions to be hierarchized/prioritized.

Fine proposes to jointly analyze factors of the system under study (internal factors) and threats coming from the external environment (external factors), in order to identify, assess, and prioritize the potential risks that external threats can adversely affect the internal factors of the system and, consequently, cause damage. Quantitatively, prioritization arises from putting values on these factors and assigning a risk value that is a product of the probability of occurrence of the threat, the (frequency of) exposure to the threat, and the severity of the consequences [14].

Most current methods simply multiply the probability of occurrence by the severity of the consequences or impacts. One of them, widely disseminated, is the method advocated by the INSHT of Spain in its NTP 330 [15]. This is a simplified method, based on levels or intervals of occurrence and not on values themselves. The risk level (RL) is considered to be the multiplication of a probability level (PL) by a consequence level (CL). In turn, the PL value arises from the product of the deficiency level (DL) and the exposure level (EL). The value of DL connects risk factors in terms of their possible direct relationship with the occurrence of an accident. This is a concept analogous to that of vulnerability; the higher the DL, the greater the probability that the accident will occur, as long as there is a least frequent EL (not occasional or sporadic) at the same time. Thus, the PL can be very high, high, medium or low. Regarding the level of consequences, they can be classified as mild, serious, very serious, or catastrophic (in the case of accidents, they are said to be fatal). By crossing both values, the risk level and the intervention level are obtained, which can be ordered into four categories: intervention level I (critical situation that needs urgent correction); intervention level II (correct and adopt control measures); intervention level III (improve if possible; it would be convenient to justify the intervention and its profitability); intervention level IV (do not intervene, unless a more precise analysis justifies it) [15].

Universidad del Litoral [16] takes up this method and makes two valuable adjustments, which are to convert the consequences to monetary costs and to define in a simpler way the scores for the evaluation of exposure and probability (thinking about accidents at work). It also simplifies the intervention categories, according to the degree of danger of each risk: high (immediate intervention to end or treat the risk); medium (short-term intervention); or low (long-term intervention or tolerable risk) [16].

Once the different risk magnitudes have been obtained, it is necessary to obtain the severity of consequences; in occupational safety, it is quantified according to the repercussions level, which refers to the number of people exposed to the considered danger. Finally, it is possible to have an order of action priorities, always starting with those that are in the high danger-high repercussion zone. Significant risks will consider those whose degree of prioritization is high and medium with a high, medium, or low repercussion, respectively. The severity level may be reduced if corrective measures are applied that reduce any of the factors, consequences, exposure, and probability, so the importance of prioritization would change. In [16], the matrix in Table 1 is attributed to INSHT.

Risk levels – Consequences levels.
ProbabilitySlightly HarmfulHarmfulExtremely Harmful
Low LTrivial riskTolerable riskModerate risk
Medium MTolerable riskModerate riskMajor risk
High HModerate riskMajor riskIntolerable risk

Table 1.

Risk factor matrix for occupational accidents (adapted from [16]).

Two other possible scales of interest arise from [17]: a probability of occurrence scale and a scale to justify the investment.

Probability scale: almost certainly (it is the most possible result); very possible (almost possible, 50% probability); possible (it is a rare but possible coincidence); hardly possible (it is a very rare coincidence, but it has already happened); remote (extremely rare but conceivable); almost impossible (it has never happened in several years of exposure).

The scale to justify the investment to be made is proportional to the percentage of reduction of risk. It has three levels: in-doubt investment, normally justified investment, and fully justified investment [17].

Advertisement

2. Case study

The case study relates to an inter-institutional experience within the framework of the Road Rehabilitation and Maintenance Program 8733-UY financed by the World Bank. It was carried out between the Department of Environmental Engineering of the Institute of Fluid Mechanics and Environmental Engineering (DIA-IMFIA) of the Faculty of Engineering of the Universidad de la República (FING-UdelaR) and the Ministry of Transportation and Public Works (MTOP) of Uruguay, through its National Administrations in Planning and Logistics, Highways, and Topography [4, 7]. The objective was to satisfy certain contractual commitments related to the resilience of road infrastructure in the face of climate change, which involved the development of three technical reports associated with the evaluation of existing infrastructure in the face of hydrometeorological events. A working group was formed ad hoc, called “Road Resilience to Climate Change Group” (hereinafter, GRVCC). The work team was very successful in technical analysis, discussion, and exchange, which allowed for building and putting into practice an effective and robust methodology; solid results were obtained to achieve the pursued objectives [4, 7, 18].

The methodology to be applied was framed in the current approach of the IPCC on vulnerability and risk [3], which focuses on events of lower intensity but with a higher probability of occurrence. The Ministry’s Engineers selected a set of 20 bridges expected to have greater vulnerability to intense hydrometeorological events, due to their location, age, characteristics, and history of the last 25 years [7]. This type of event has been hitting Uruguay with increasing frequency and intensity in recent years [19]. For this set of bridges, a detailed analysis of its characteristics was carried out by modeling for events with three return periods with the free-use software HEC-RAS [20] was performed, supported by the open-source GIS software QGIS. In this case, the simulations were made by using three different precedent soil moisture conditions (dry, medium, and humid) [21] and for three return periods (Tr = 50 years, Tr = 100 years, and Tr = 1000 years) [7, 18].

The direct and indirect socioeconomic costs derived from its occurrence were evaluated, with the objective of not only anticipating attention to adverse impacts but also allocating sufficient resources to monitoring and preparation tasks and strengthening the resilience of the communities. The allocation of devoted resources to these latter aspects is part of the necessary cultural change that current societies are forced to assume due to climate change [18, 19].

Risk matrices were built to present the information obtained in a compact and clear form. In the last stage of work, contingency plans were prepared for two of the cases studied [18, 19]. The background and procedures that the National Emergencies Agency (SINAE) has implemented in conjunction with the Departmental Emergencies Coordination Centers (CECOED) were taken as a starting point, taking into account both the successful practices and the opportunities for improvement that the institutions had detected from their application [22].

Advertisement

3. The risk matrices used in this case study

3.1 Planning the matrices’ contents

A risk matrix is a very practical technique and visual tool for analyzing and communicating information regarding the possibilities that “something”, and in this case, a bridge will fail due to the intrinsic characteristics that make it vulnerable to threats, that is, what makes prone to damages due to its occurrence as well as the type and magnitude of the consequences that could be expected in case that the threat actually occurred. The matrix has a double-entry table in which vulnerability factors and danger factors are interrelated to identify and prioritize the consequences on the infrastructure that may cause different magnitudes of hydrometeorological events [7].

Vulnerability factors are those characteristics of a bridge—including its immediate environment—that make it more prone to failure. They refer to the intrinsic disposition to suffer harm. Danger factors, on the contrary, depend on hydrometeorological events rather than on the bridge. The factor that is usually considered most representative of its probability of occurrence is the return period. Thus, the methodology consists on crossing these factors and assigning them a value that reflects the probability of occurrence and the severity of events consequences. The scales to quantify probability and severity can be quantitative, qualitative, or a combination of both [7, 18].

To assemble and fill out the matrix, adequate information must be available on both the infrastructure characteristics and conditions under study and the events to be considered to identify and evaluate the resulting risks in each interaction cell. The sensitivity of this tool lies primarily in the choice of probability and severity scores given to each interaction [7, 19].

According to [23], the case study is an application that can be qualified as “Triple baseline analysis (environmental, social and economic)” with high-level screening. Depending on the information available, the quality of the information obtained will be determined and the list of points in which improvement is needed will be known.

In this case, the probability of occurrence has been assigned in a decreasing manner to events with a return period of 100, 200, and 500 years, while the severity of the consequences was managed according to intervals defined for each type of effect. The severity can be assigned based on experience and professional criteria: flooded area and its use, including type of crop, livestock, etc., foreseeable number of evacuees, among others. Socioeconomic criteria will also be considered, such as the characteristics of the routes that would be interrupted if a road were not passable and the economic consequences depending on the type and quantity of vehicles and freights that travel on that road [7, 18].

The impact levels considered are shown in Table 2, and the levels of probability of occurrence are presented in Table 3.

Expected impactDefinition
Severe (3)Impacts that could greatly affect (in quantity and severity) the community, infrastructure, and environment.
Moderate (2)Impacts that could moderately affect (in quantity and severity) the community, infrastructure, and environment.
Low (1)Restricted impact, with little and weak impact on the community, infrastructure, and environment.

Table 2.

Impact levels (adapted from [7]).

The color code is inspired by that of a traffic light.


Probability of occurrenceDefinition
High (3)The threat has already materialized in the location and with high frequency, or there are very strong indications of its future occurrence.
Medium (2)The threat has manifested itself with medium frequency, or although it has not manifested itself, there are important indications of its future occurrence.
Low (1)The threat has never materialized or has done very little, and there are no or very slight signs indicating its future occurrence.

Table 3.

Levels of probability of occurrence (adapted from [7]).

The color code is inspired by that of a traffic light.


By the multiplication of the probability of occurrence and the impact severity, the results should be classified into the five classes, as defined in Table 4.

Impact
LowModerateSevere
ProbabilityHighModerate Risk (3–4)Major Risk (6)Inadmissible Risk (9)
MediumTolerable Risk (2)Moderate Risk (3–4)Major Risk (6)
LowAdmissible Risk (1)Tolerable Risk (2)Moderate Risk (3–4)

Table 4.

Risk levels (adapted from [7]).

The color code is inspired by that of a traffic light.


The results end up categorized according to the color code shown in Table 5, depending on the risk value [7, 18].

Probability1 Low; Tr = 5002 Medium; Tr = 2003 High; Tr = 100
Severity1 Low1 – Admissible2 – Tolerable3 – Moderate
2 Moderate2 – Tolerable4 – Moderate6 – Major
3 Severe3 – Moderate6 – Major9 - Severe

Table 5.

Color code for risk matrices (adapted from [7]).

The color code is inspired by that of a traffic light.


In the case of a bridge failure, that is to say, the bridge falling down, the vulnerability was taken as the risk value, as presented in Table 6; the consequences considered were only those related to the connection between the closest cities on both sides of the bridge and the impact on freight traffic and tourism.

LowMediumHigh
Number of households affectedUp to 30Between 30 and 100More than 100
Number of inhabitants affectedUp to 100Up to 300More than 300
Services affectedNoEducationHealth/Education and health
Road cutUp to 500 mBetween 500 and 5 kmMore than 5 km
Freight transportNoSeasonalDaily (milk products, port)
TourismNoSeasonalAll year
Forests, grasslands, natural fieldsUp to 1 km2From 1 to 10 km2From 11 to 100 km2
Urban and urbanized areasUp to 0,05 km2From 0,05 to 0,1 km2More than 0,1 km2
Dry crops and stubbleUp to 0,25 km2From 0,25 to 1 km2More than 1 km2
Rice and stubble cultivationUp to 0,5 km2From 0,5 to 5 km2More than 5 km2
Beaches, dunes, fixed, and semifixed dunesUp to 0,1 km2From 0,1 to 0,5 km2More than 0,5 km2
Extensive crops on dairy farmsUp to 0,5 km2From 0,5 to 1 km2More than 1 km2
Quarries, sand pits, open pit minesUp to 0,1 km2From 0,1 to 0,5 km2More than 0,5 km2
Horticultural zoneUp to 0,05 km2From 0,05 to 0,2 km2More than 0,2 km2
Lost cattleUp to 50From 51 to 500More than 500

Table 6.

Consequences to evaluate (adapted from [7]).

3.2 Vulnerability factors

The vulnerability analysis involves considering a set of factors specific of the bridge and its circumstances (location, state of conservation, etc.), which are those that make it more prone to failure. These characteristics have been grouped according to the type and severity of the failure, for which the structure is more sensitive: factors related to the flow velocity; factors related to the occurrence of scour; and other factors that could be related to possible failure of the structure (Table 7) [4, 7].

Factors related to flow velocity in the bridge sectionFactors directly related to scourOther factors related to possible failure of the structure
SpanPiles shapeThickness of the bridge deck
Spacing between pilesType of foundationStructural status
Orientation related to the axis of the watercourseState of the banksConcentration of water flows
Location section on the watercourseLocalized scour in the piles
Presence of singular elements that may be obstacles to flowLocalized scour in abutments
Sediment accumulation by the bridge structure

Table 7.

Vulnerability factors (adapted from [4]).

The characteristics of the bridges that were finally included in the risk analysis are presented in Table 8. They are grouped in piles, deck and foundation characteristics, concentration of water flows, cut section, bank conditions, presence of possible obstacles, localized scour in piles or abutments, sediment accumulation, and structural status of the bridge [7].

ParametersCategoriesInterpretation
PilesPiles shapeSquareThese are the most unfavorable options for scour.
Pointed
CircularThey are the best options for scour.
group of cylinders
Number of pilesIt is used together with the span to calculate the spacing between piles. If the separation is less than 10 m it is considered the highest degree of vulnerability, while if it is greater than 20 m, it will be the lowest.
OrientationPerpendicular
skew
DeckThicknessLess thickness implies greater structural vulnerability
span
Type of foundationsdirectThe direct foundation reduces the possibilities and magnitude of scour.
Pilotage
Concentration of water flowsYesThe concentration of flows near the bridge increases its vulnerability.
No
Cut sectionStraight sectionLocation on a straight section reduces vulnerability.
meander
Bank conditionVegetation with maintenanceVegetated options reduce vulnerability, while bare banks increase it.
Vegetation without maintenance
bare banks
Presence of singular elements that can result in obstaclesYesFree flow reduces vulnerability.
No
Localized scour in the pilesNot detectedThe greater the scour, the greater the vulnerability to possible structural failure.
moderate
critic
Scour in abutmentsNot detectedThe greater the scour, the greater the vulnerability to possible structural failure.
moderate
critic
Sediment accumulation by the bridge structurevisibleThe presence of visible sedimentation increases the speed of passage by reducing the runoff section. This increases the vulnerability of the bridge.
Not visible
Structural statusGoodIf the structural condition is not good, vulnerability and the possibilities of structural failure increase.
Regular

Table 8.

Considered characteristics (adapted from [7]).

By using these criteria, it was obtained that almost half of the bridges in the sample were considered low vulnerability to failure, while only three were categorized as very vulnerable [7].

3.3 Threat factors and severity of consequences

The existence of risk implies, by definition, the potential presence of danger, that is, an agent that is likely to cause harm. These agents will be of different natures and entities. To evaluate the risks, some questions must be answered, such as what could happen? When could it happen? How would it happen? What is the probability of it happening? If it happens, what would be the consequences? To do this, it is necessary to propose an analysis of the threat or danger [4, 7, 18, 19].

The threat factors are independent of the infrastructure and are linked, in this case, to hydrometeorological events. Thus, to prepare a list of threat factors, it is useful to understand danger as the probability of a harmful phenomenon occurring of a certain intensity, during a certain period of time, which will depend on the physical-geographical characteristics of the place. It is important to have enough information about the recent, historical, and projected climate in the study area. When it is possible, historical infrastructure responses to climate change will be also considered (PIEVC, 2011 as referred in [5]).

In the case of floods, it is necessary to obtain reliable data on the physical characteristics of the affected area and its population (size, distribution, density, economic and cultural characteristics, education, health coverage, among others) [7]. The effects of the storms studied refer to the destruction of physical assets (damage) and the alteration of economic flows (losses and additional costs). Consequently, it is necessary to know in the most quantitative way possible the previous situation—in general through quantitative information published by official sources or documents based on them—as well as the damages, losses, and additional costs caused by these disasters, in order to be able to carry out a quantification of its costs and impacts as precise as possible. As the study aims to quantify the greatest possible number of aspects of interest, it is proposed to quantify parameters of each bridge and its immediate environment before and after the occurrence of the adverse hydrometeorological event being studied and to attempt to quantitatively assess the impact, based on the differences between both conditions. It also includes an economic quantification [7, 18, 19].

The main consequences could be that the deck height of non-submersible bridges is exceeded, that submersible bridges remain out of service for longer than considered in their design; the increase of localized erosion in piles and abutments, and that the structure fails as a consequence of one or more of the aforementioned effects. Likewise, considering the bridge integrated into its closest environment, the severity of other consequences related to floods and, consequently, the losses generated due to the dangerous event must also be taken into account [7, 18].

It is also necessary to consider the severity of the effects of losing road connectivity. The latter is related to the type of load transported on that section of the route, the proximity to ports and national borders, the towns it connects and the services that each one has, the existence of alternative connection options with other towns during traffic interruption, among others. The evaluated consequences, which are classified according to their severity, are listed in Table 6, with the categories considered in each case [7, 18].

Other factors that were taken into account when assessing the severity of the consequences are the greater or lesser interdependence of the localities closest to either side of the bridge (high vulnerability was considered when the population of one of them was more than triple the population of the other), the annual average daily traffic (less than 500 vehicles was considered a low level of traffic while more than 2000 was considered high), and the proximity to borders and ports (more weight was given to the proximity to the ports of Montevideo and Nueva Palmira, and in second place, the dry borders and binational bridges) [7, 18].

The threats or dangers considered were hydrometeorological events with different return periods: 100, 200, and 500 years, and the structural failure of the bridge [7].

3.4 Applications

The risk matrices corresponding to each of the considered bridges are included in [7]. Two of the main cases are also discussed in more detail in [18]. These two cases have been chosen to be presented in this chapter. The first case refers to a bridge on National Route 18, located near the entrance to the town of Vergara, in the east of the country, and the other one is the bridge over Arroyo Colla on National Route 2. The expected impact levels matrixes and the subsequent risk matrixes are presented in Tables 912.

Road interruption during less than 72 h*Long-term road interruptionFailure
(Tr = 100, 200 y 500 years)
Number of households affected in Vergara townLess than 30Between 30 and 100Between 30 and 100
Number of inhabitants affected in Vergara townLess than 100Less than 100Between 100 and 300
Affected servicesNoNoNo
Interruption Road 18ModerateModerateSevere
Interruption Route 91ModerateModerateModerate
Interruption Road 8LowLowLow
Transport of freightsModerateSevereSevere
Forest, grasslands, natural fieldsModerateModerateModerate
Urban and urbanized areasModerateSevereSevere
Dry crops and stubbleLowLowLow
Rice and stubble cultureModerateModerateSevere
Lost cattleModerateMore than 3000More than 3000

Table 9.

Expected impact levels for Route 18 (adapted from [18]).

This type of event occurs for Tr less than 100 years. The color code is inspired by that of a traffic light.


Impact
LowModerateSevere
ProbabilityHIGH
Road interruption of low permanence
Moderate Risk (3): Affected households in Vergara/Affected inhabitants in Vergara/Affected services/Road 8 interruption/Dry crops and stubbleMajor Elevado (6): Road 18 interruption/Road 91 interruption/Freight interruption/Forest, grasslands, natural fields/Urban and urbanized areas/Rice and stubble culture/Lost cattleInadmissible Risk (9): Not detected
MEDIUM Road interruption longer than 72 hTolerable Risk (2): Affected inhabitants in Vergara/Affected services/Road 8 interruption/Dry crops and stubbleModerate Risk (4): Affected households in Vergara/Road 18 interruption/Road 91 interruption/Forest, grasslands, natural fields/Rice and stubble cultureMajor Risk (6): Freight transport/Urban and urbanized areas/Lost cattle
LOW Failure/collapse of the bridgeAdmissible Risk (1): Affected services/Road 8 interruption/Dry crops and stubbleTolerable Risk (2): Affected households in Vergara/Affected inhabitants in Vergara/Road 91 interruption/Forest, grasslands, natural fieldsModerate Risk (3): Road 18 interruption/Freight transport/Urban and urbanized areas/Rice and stubble culture/Lost cattle

Table 10.

Risk matrix for Route 18 (adapted from [18]).

The color code is inspired by that of a traffic light.


Road interruption during less than 72 h*Long-term road interruptionFailure
(Tr = 100, 200 and 500 years)
Number of affected households in Rosario cityMore than 100More than 100More than 100
Number of affected inhabitants in Rosario cityVariableMore than 300More than 300
Affected servicesNoNoNo
Road 2 interruptionModerateModerateSevere
Road 1 interruptionModerateModerateModerate
Road 61 interruptionLowLowModerate
Road 52 interruptionLowLowModerate
Freight transportLowModerateSevere
TourismLowLowModerate
Forests, grasslands, natural fieldsModerateModerateModerate
Urban and urbanized areasModerateModerateModerate
Dry crops and stubbleLowLowLow
Beaches, dunes, fixed and semifixed dunesNoNoNo
Extensive drops on dairy farmsNoNoNo
Lost cattleModerateMore than 400More than 600

Table 11.

Expected impact levels for Route 2 (adapted from [18]).

This type of event occurs for Tr less than 100 years. The color code is inspired by that of a traffic light.


Impact
LowModerateSevere
ProbabilityHIGH
Road interruption of low permanence
Moderate Risk (3): Affected services/Road 61 interruption/Road 52 interruption/Freight transport/Tourism/Dry crops and stubble/Beaches/Extensive crops on dairy farmsMajor Risk (6): Affected inhabitants in Rosario city/Affected households in Rosario city/Road 1 interruption/Road 2 interruption/Grasslands/Urban areas/Lost cattleInadmissible Risk (9): Not identified
MEDIUM
Road interruption longer than 72 h
Tolerable Risk (2): Affected services/Road 61 interruption/Road 52 interruption/Tourism/Dry crops and stubble/Beaches/Extensive crops on dairy farmsModerate Risk (4): Affected households in Rosario city/Road 1 interruption/Road 2 interruption/Freight transport/Grasslands/Urban areasMajor Risk (6): Affected inhabitants in Rosario city/Lost cattle
LOW
Failure/collapse of the bridge
Admissible Risk (1): Affected service/Dry crops and stubble/Beaches/Extensive crops on dairy farmsTolerable Risk (2): Affected households in Rosario city/Road 1 interruption/Road 61 interruption/Road 52 interruption/Tourism/Grasslands/Urban areasModerate Risk (3): Affected inhabitants in Rosario city/Road 2 interruption/Freight transport/Lost cattle

Table 12.

Risk matrix for Route 2 (adapted from [18]).

The color code is according to that of Table 5. The color code is inspired by that of a traffic light.


3.4.1 Route 18: entrance bridge to Vergara town

The entrance to Vergara town is an old bridge over Arroyo Parao. Its location is sketched on a map of Uruguay in Figure 1(a). The town has another entrance, the bridge on Route 91; it is also close to International Route 8, one of the most active land freight transportation routes in Uruguay.

Figure 1.

(a) Location of Vergara town and its entrance bridge. (b) Affected zone in first 24 hours of flooding. (c) Affected zone for Tr = 500 years (from [7]).

The damage and losses associated with the 100-year return period flood are not very different from those with 200-year and 500-year return periods. The difference focuses on a short-term or long-term interruption of the route by the flood.

The short-term interruption of the route affects 27 households and 86 inhabitants; the long-term interruption affects 38 households and 122 inhabitants. The estimated costs of these damages are approximately US$ 1.249.000 and US$ 1.740.230, respectively. The costs of evacuating people and transitional housing are US$ 18.600 and US$ 22.600 more in each case.

No educational or health services are expected to be affected.

Freight transport is expected to be affected moderately and severely, respectively; approximately, 20.500 tons cannot reach their destination on time. In the worst case, they have an estimated cost of US$ 1.320.000.

Large areas of rice culture are expected to be affected: 6,7 km2 in the short-term flood and 10,1 km2 in the long-term one. In both cases, only small areas of dryland crops are expected to be affected. The estimated costs are approximately US$ 1.052.000 and US$ 1.577.000, respectively.

The loss of livestock is the last major cost to be considered: more than 3100 heads of cattle or US$ 3.845.000 in the first case and more than 3530 heads of cattle or US$ 4.378.500 in the second one.

The estimated cost of managing a short-term flood is approximately US$ 7.450.000, including damage and losses; in the case of a long-term flood, it is about US$ 9.100.000.

The information on Table 9 is used to complete the cells of Table 10, considering the situations in Table 5: high probability of occurrence and severe impacts are not admissible, while low probability of occurrence and low severity of impacts are admissible; and all intermediate ratings as shown in Table 5.

As a result, no inadmissible risk situations are detected, but many major and moderate risk situations have been identified as well as others of tolerable and admissible risk.

3.4.2 Bridge over arroyo Colla

The bridge over Arroyo Colla was built in 1917. Its location is sketched on a map of Uruguay in Figure 2(a). It is close to Rosario town, in the department of Colonia. The town is also close to other routes: International Route 1, which connects Montevideo with the city of Colonia and with Buenos Aires (Argentina) through its international passenger port; and National Routes 52 and 61, which connect Rosario with nearby productive areas (crops, livestock, dairy farms).

Figure 2.

(a) Location of the bridge over Arroyo Colla. (b) Affected zone in first 24 hours of flooding. (c) Affected zone for Tr = 500 years (from [7]).

This case is similar to the previous one: the damage and losses associated with the 100-year return period flood are not very different from those with 200-year and 500-year return periods. The most important thing is the permanence of the interruption of the route due to the flood.

The short-term interruption of the route affects 105 households and 336 inhabitants; the long-term interruption affects 123 households and 394 inhabitants. The estimated costs of these damages are approximately US$ 7.248.000 and US$ 8.568.000, respectively. The costs of evacuating people and transitional housing are US$ 61.000 and US$ 62.700 more in each case.

Also in this case, no educational or health services are expected to be affected.

Freight transport is expected to be affected, moderately and severely respectively; approximately, 16.300 tons cannot reach their destination (e.g., Nueva Palmira International Port) on time. Given that it is an international port that there are more sensitive merchandise involved and also that the tourist connection through the port of Colonia may be affected; the losses are estimated at US$ 6.250.000.

Dryland crops areas are expected to be affected: 1,5 km2 in the short-term flood and 1,75 km2 in the long-term one. The estimated losses are approximately US$ 93.000 and US$ 108.000, respectively.

The loss of livestock is the last cost to be considered: 430 heads of cattle or US$ 2.304.000 in the first case and more than 650 heads of cattle or US$ 2.504.700 in the second one.

The estimated cost of managing a short-term flood is approximately US$ 16.000.000, including damage and losses; in the case of a long-term flood, it is about US$ 17.600.000. These high figures are mainly related to the large urban areas affected by the flood and the interruption of freight transportation to the Nueva Palmira International Port, the second cargo port in Uruguay.

In the same way, as the previous case, the information on Table 11 is used to fill in the cells of Table 12, considering the cases in Table 5.

No inadmissible risk situations are detected, but many major and moderate risk situations have been identified as well as others of tolerable and admissible risk.

Advertisement

4. Conclusions

Successful adaptation to climate change is based on a multidimensional perspective that encompasses social, economic, environmental, and institutional aspects. Therefore, risk and vulnerability assessments intended to inform these adaptation strategies also require a multidimensional perspective.

An integrated and interdisciplinary approach makes it possible to greater certainty when addressing the complexity and dynamics of social and environmental systems and contribute to more effective risk management by the different actors involved in making decisions on risk reduction or adaptation.

Simple but effective elements, such as William Fine’s risk analysis matrix adapted to the case study, may produce extremely effective results in the synthesis, assessment, and communication of information.

Advertisement

Acknowledgments

The authors thank the Ministry of Transportation and Public Works for financing the project through an agreement with the Julio Ricaldoni Foundation of the Faculty of Engineering, UdelaR, and for authorizing the publication of this work.

They also sincerely thank all the members of the Climate Change Road Resilience Group, the inter-institutional team that carried out this project: Arch. Rafael Ferrando, Mag. Eng. Hebenor Bermúdez, Mag. Eng. Gabriela Acosta† from MTOP; and Eng. Malena López Parard, Eng. Micaela Luzardo Rivero and Eng. Juan Ignacio Pais from DIA-IMFIA (FING-UdelaR).

Advertisement

Conflict of interest

The authors declare no conflict of interest.

References

  1. 1. Renssnature & Consulting Cía. Ltda. Capítulo X Análisis de Riesgos (para Petroamazonas). Ecuador: Gruporenss; 2016. p. 2016
  2. 2. Dirección General de Alianzas Público Privadas DGAPP. Metodología de Análisis de Riesgo. República Dominicana: DGAPP; 2020
  3. 3. Cardona OD, van Aalst MK, Birkmann J, Fordham M, McGregor G, Perez R, et al. Determinants of risk: Exposure and vulnerability. In: Managing the Risks of Extreme Events and Disasters to Advance Climate Change Adaptation. A Special Report of Working Groups I and II of the Intergovernmental Panel on Climate Change (IPCC). Cambridge, UK, and New York, NY, USA: Cambridge University Press; 2012. pp. 65-108
  4. 4. Grupo Resiliencia Vial al Cambio Climático. Informe: Fase I. MTOP - FJR. Montevideo, Uruguay: Grupo Resiliencia Vial al Cambio Climático; 2019. 23 p
  5. 5. Sandink D, Lapp D. The PIEVC protocol for assessing public infrastructure vulnerability to climate change impacts: National and international application. In: CSCE 2021 Annual Conference, Canada. May 2021
  6. 6. Engineers Canada/Ingénieurs Canadá. Public Guideline on Risk Management. Canadá: Engineers Canadá; 2020
  7. 7. Grupo Resiliencia Vial al Cambio Climático. Producto 2: Análisis de detalle de veinte puentes. MTOP - FJR. Montevideo, Uruguay: Grupo Resiliencia Vial al Cambio Climático; 2020. 143 p
  8. 8. Silveira L, Genta JL, Charbonnier F, Failache N, y Alonso, J. Directivas de diseño hidrológico – hidráulico de alcantarillas. Uruguay: Universidad de la República, Facultad de Ingeniería, IMFIA; Ministerio de Transporte y Obras Públicas, Dirección Nacional de Vialidad; 2000
  9. 9. Unión Europea. Directiva 2007/60/CE del Parlamento Europeo y del Consejo, de 23 de octubre de 2007, relativa a la evaluación y gestión de los riesgos de inundación. Belgium; 2007
  10. 10. Nixon S, Horn J, Hödl-Kreuzbauer E, ter Harmsel A, Dominique VE, Thomas D. European Overview Assessment of Member States’ Reports on Preliminary Flood Risk Assessment and Identification of Areas of Potentially Significant Flood Risk. Luxembourg: Publications Office of the European Union; 2016. DOI: 10.2779/576456
  11. 11. European Commission DG. Science for Environment Policy: Responding to Floods in Europe: New Framework Assesses Effectiveness of Flood Emergency Management Systems Environment News Alert Service, Edited by SCU. Bristol: The University of the West of England; 2017
  12. 12. Gilissen HK, Alexander M, Matczak P, Pettersson M, Bruzzone S. A framework for evaluating the effectiveness of flood emergency management systems in Europe. Ecology and Society. 2016;21(4):27. DOI: 10.5751/ES-08723-210427
  13. 13. Veleda S, Martínez-Graña A, Santos-Francés F, Sánchez-San Roman J, Criado, M. Analysis of the hazard, vulnerability, and exposure to the risk of flooding (Alba de Yeltes, Salamanca, Spain). Applied Sciences. 2017;7(2):157. DOI: 10.3390/app7020157
  14. 14. UNIR Revista. 2023. El método William T. Fine para el análisis de riesgos laborales - 26/12/2023. Available from: https://www.unir.net/ingenieria/revista/metodo-william-t-fine/
  15. 15. Belloví B, Malagón P. NTP 330: Sistema simplificado de evaluación de riesgos de accidente. España: Instituto Nacional de Seguridad e Higiene en el Trabajo, Centro Nacional de Condiciones de Trabajo, Ministerio de Trabajo y Asuntos Sociales; s.f
  16. 16. Universidad Nacional de Litoral UNL (s.f.). Diagnóstico Situacional - Control de Riesgos. Available from: http://www.eis.unl.edu.ar/z/adjuntos/2994/Control_de_Riesgos.pdf
  17. 17. Qué es el método de evaluación W. Fine. Available from: https://seguridadindustrial77.blogspot.com/2017/11/metodo-de-evaluacion-w-fine.html
  18. 18. Grupo Resiliencia Vial al Cambio Climático. Producto 3: Planes de Contingencia. MTOP - FJR. Montevideo, Uruguay: Grupo Resiliencia Vial al Cambio Climático; 2020. 67 p
  19. 19. González-Fernández AE, Paz-Urban M, Goyeneche M. Análisis de vulnerabilidad de obras viales en Uruguay ante el cambio climático. Quivera Revista de Estudios Territoriales. 2022;24(2):5-27. DOI: 10.36677/qret.v24i2.19349
  20. 20. US Army Corps of Engineers, Hydrologic Engineering Center. HEC-RAS River Analysis System. User’s Manual, Version 5.0. USA: US Army Corps of Engineers, Hydrologic Engineering Center; 2016
  21. 21. Papaioannou, G., Loukas, A. y Vasiliades, L. (2019). Flood risk management methodology for lakes and adjacent areas: The Lake Pamvotida paradigm. Proceedings, 7 (21), doi: 10.3390$/$ECWS-3-05825
  22. 22. SINAE. Informes de consultorías Generación de conocimientos en Gestión Integral del Riesgo. Guía. 2014;6:211-226
  23. 23. PIEVC Global Partnership. PIEVC© Family of Resources Catalogue. A Guide for Selecting Climate Risk Assessment Methods, Data, and Supporting Materials. Canadá: Public Infrastructure Engineering Vulnerability Committee PIEVC; 2021

Written By

Alice Elizabeth González, Martín Paz Urban, Martín Goyeneche and Lady Carolina Ramírez

Submitted: 07 May 2024 Reviewed: 15 May 2024 Published: 18 June 2024